Construction Report for November 27, 2018

Construction Project Report

 

To be let:

 

FM-CO97(136)—55-97, D38 HMA resurfacing project between Bronson and the Moville Blacktop. Letting date: March 19, 2019.   Late start date:  to be determined.    The project involves cold in place recycling of existing pavement followed by an overlay of the pavement with new hot mix asphalt pavement.   Work will be done in 2019.

 

FM-C)97(137)—55-97, K49 HMA resurfacing project between Plymouth County line and county route D12.   Letting date: February 19, 2019.   Late start date:  to be determined.   This project is being done in coordination with a Plymouth County project on the same county route.   The project involves cold in place recycling of the existing pavement followed by an overlay of high performance asphalt surfacing.    The high-performance surface provides a thinner overlay on top of the recycled pavement than standard hot mix asphalt.   This is Woodbury County’s first project using this material.  Work will be done in 2019.

 

Under Contract:

L-B(U51)—73-97, 320th Street Bridge replacement.   Letting date: October 30, 2018.   Late start date:  April 15, 2019.   Contractor: Graves Construction, Spencer, IA.  Contract price:  $475,343.66. Working days: 65. This bridge has been closed since 2014 due to a failed substructure piling.

The project will allow winter work at the contractor’s option.   We are awaiting a request for a preconstruction meeting from the contractor and expect him to move in within the next two weeks.

 

BROS-CO97(133)—55-97, Hancock Avenue Bridge replacement. Letting date:  October 16, 2018 (IDOT Letting) Late start date: June 17, 2019.   Working days: 85.   Contractor: Dixon Construction.   Bid Price: $567,393.30.  This project replaces an aging truss bridge on Hancock Avenue near the 200th Street intersection.  The current bridge is posted 3 tons.

            The project contract has been signed and approved by Iowa DOT.   After the contractor requests a preconstruction meeting, we will know when the start date for construction will be.   The project schedule allows winter work that may allow the bridge project to be completed earlier in 2019.  

 

 

STP-S-CO97(134)—55-97, D50 PCC Resurfacing near Oto. Letting date:  April 17, 2018.   Late start date: July 23, 2018.   Working days: 60.  Contractor: Cedar Valley Corporation, Waterloo, IA.  Contract price:  $2,354,844.71. 

            All mainline paving is complete.   The bridge approaches on the Little Sioux River bridge have been poured and should be ready for traffic by Thursday.   Shouldering is complete up to Morgan Trail with only the segment between Morgan Trail and Highway 31 remaining.  The guardrail subcontractor is coming on Tuesday to install new guardrail on the river bridge east of Oto.   The project should reopen to traffic Thursday, November 29 after pavement markings are applied.

 

BROS-CO97(132)—55-97, 150th Street Bridge replacement near Lawton.  Letting date:  June 19, 2018 (IDOT Letting). Late start date: May 1, 2019.   Working days: 105.   Contractor: Dixon Construction, Correctionville, IA.  Contract price:  $1,019,550.42.   This project replaced an aging truss bridge on 150th Street (Old Highway 20) north of Lawton.

The bridge removal is complete and channel excavation for the new bridge opening is almost completed. The contractor is going to drive east pier pile on the bridge this week.   Work will continue as weather allows through the winter.

 

L-B(J9)—73-97, County Bridge J9 is on 170th Street between Jasper and Jewell Avenues. Letting date:  August 21, 2018.  Late start date:  April 15, 2019.  Contractor: Dixon Construction, Correctionville, IA.  Contract price:  $544,821.40. This bridge was one of the flood damaged structures from the June 18, 2016 storm event.   The bridge has been closed to traffic since it was damaged in the flood.

            The contractor is replacing county road closed signs with new traffic control.   Removal of the old bridge should begin this week.   Work will continue through the winter as weather allows.

 

Work Under Design:

 

Design work is underway on the following projects for letting sometime during 2018 and 2019.

 

250th Street Grading Project -  2.25-mile grade for paving project south of Anthon.   Right of way will be necessary to allow construction of this road.   Final design is complete.   Plats for right of way acquisition are complete and acquisition has started.  We have been delayed in further right of way negotiations in cooperation with landowners who have been busy with fall harvest.   We hope to resume right of way acquisition in December after harvest.   We are working toward a winter 2018 letting.  This project is funded with the $1.3 million per year special project levy funds.

 

Bridge D156 – This structure is on Franklin Avenue north of Old Highway 20/150th Street.  The structure is posted 8 tons.   The existing structure is significantly oversized and built from salvaged materials.   The replacement structure is proposed to be a large culvert.  This project is funded with money received in the local budget from the new $0.10 state fuel tax.  The project is scheduled for early 2019 construction.

 

            Haskell Avenue Bridge C-160 -  Design work and permitting are complete on the Haskell Avenue Bridge.   The new bridge will be a single span 100’ x 30.5’ pretensioned, prestressed concrete beam bridge.   Final plans are being prepared for a March 2019 letting.

 

Gravel crushing is underway at both the Railroad pit and the Briese pit. About 17,000 tons has been processed at the Railroad pit.    The crusher at the Briese pit broke down last week and production is just starting for the contract quantity.  

 

Mason Avenue Bridge:

            The Mason Avenue bridge was severely damaged by flooding on the Little Sioux River in July 2018.   The bridge has been closed to traffic due to damage caused by the bridge being struck by

a large tree.   The county engineer’s office was notified Wednesday that FEMA has determined that the damage is eligible for repair/replacement assistance.  The county road department is filing preliminary documentation requesting assistance from FEMA for assistance with eligible costs and will be having an applicant briefing on Tuesday, October 16th.   Communication is open with FEMA at this time to replace the existing bridge.   We expect that work to be completed in 2020 at this time.