Woodbury County FY 2021 to FY 2025 Construction Program

On April 7, 2020, the Woodbury County Board of Supervisors approved the Secondary Road Department Five Year Construction Program.   The program has a total of $30,817,000 in bridge replacement and road improvement projects scheduled over the next five year period.   The program replaces 29 county bridges or culverts and plans the rehabilitation of 30.6 miles of the county's asphalt and portland cement concrete pavements. 

The program period begins July 1, 2020, with the beginning of Fiscal Year 2021.   The program is attached to this posting.   If you have any questions, you can contact County Engineer Mark Nahra at 712-873-3215 or This email address is being protected from spambots. You need JavaScript enabled to view it. or Project Engineer Ben Kusler at 712-873-3215  This email address is being protected from spambots. You need JavaScript enabled to view it. .  